Project profile for Tk.1.19 crore A/c. H. S. Industries Ltd.
01. Name of Project: H. S.
Industries Ltd.
02. Location of the Project:
BISIC, Chauddagram, Comilla.
03. Nature of the project: New
& Manufacturing.
04. Purpose of the project: To
Establish an export oriented spicy Industry. To create a large no. of job
opportunities which will be contributed in our National GDP.
05. Proposal: The proposal
envisages for setting up a spices processing & packaging Project under the
name & Style of H. S. Industries Ltd. at BSCIC , Chauddagram, Comilla. It
is intended to process & packages varies kinds of spices. All the products
will be marketed sourinding 3 districts like Comilla, Feni & Noakhali.
06. Project Promoters:
|
Sl
No.
|
Name
|
Address
|
Qualification
|
Experience
|
Age
|
Position
|
Share
(%)
|
|
01.
|
M
|
A
|
BA
|
25
Years
|
45
Years
|
Chairman
|
40
|
|
|
N
|
B
|
BSC
|
7
Years
|
30
Years
|
Directors
|
20
|
|
|
O
|
C
|
MA
|
5
Years
|
28
Years
|
Do
|
20
|
|
|
P
|
D
|
HSC
|
5
Years
|
25
Years
|
Do
|
10
|
|
|
Q
|
E
|
SSC
|
5
Years
|
22
Years
|
do
|
10
|
07. Organizational &
Management set up: Private Ltd Co.
08. Assets & Liabilities:
|
Assets
|
Tk.
In lac
|
Labilities
|
Tk.
In Lac
|
|
Cash:
Bank
balance:
Land
& Building:
Receivable:
Others
:
|
5
50
200
13
5
|
Owners’
Equity
Accounts
Payable
Others
|
260
10
3
|
|
Total
|
273
|
|
273
|
09. Managerial Capacity: All of
the directors work in the same line of business for different years. But the
chairman has resigned from his job to look after the business. All of the
skilled persons are well known to them. Un skilled labors are available in
Chauddagram.
10. Market reputation: All the
directors including chairman are very much reputed in their respective fields.
11. Project Duration:3 yrs
12. Land & Location
Proposed: 4 Plots has been leased in BSCIC, Chauddagram, Comilla for 99
years
09. Nature of Land: BSCIC Plot in the industrial
area.
10. Building & Civil Works:2 Godowns & 1
Factory & Office cum Dormatory to be constructed.
13. Plant & Machineries: 60
% machine to be imported & 40 % to be purchased from local market.
12.Pre-Production Cost:
|
Sl
No.
|
Items
|
Estimated
Cost
|
|
01.
|
Preparation
& Collection of up to date papers/ Documents of project land.
|
Tk.20000/-
|
|
02.
|
Collection of price quotation etc
|
Tk.10000/-
|
|
03.
|
Cost
regarding power & gas connection excluding security money
|
Tk.200000/-
|
|
04.
|
Bank’s
fee
|
Tk.20000/
|
|
05.
|
Raw
materials for trial production of the project & others start up expenses
as required
|
Tk.
150000/-
|
|
|
Total
|
Tk.400000/-
|
14. Raw materials at various
capacity levels including packaging materials for 1 yr:
|
Items
|
Quantities
|
Unit
Cost
|
Total
cost
|
|
Holud
|
200
|
8000
|
Tk.1600000
|
|
Morich
|
200
|
4200
|
Tk.840000
|
|
Dhonia
|
100
|
4000
|
Tk.400000
|
|
Poly
Bag
|
500000
pc.
|
.20
|
Tk.100000
|
|
Total
|
|
|
Tk.2940000/-
|
14. Man power:
a)Operational Management Personnel
Category |
No.
|
Monthly
wages
|
Annual
Cost
|
|
Factory
Manager
|
1
|
10000
|
120000
|
|
Production
Manager
|
1
|
8000
|
96000
|
|
Nutritionist
|
1
|
8000
|
96000
|
|
Production
Supervisor
|
5
|
5000
|
300000
|
|
Forman
(Technical)
|
6
|
4000
|
288000
|
|
Skilled
Labor
|
20
|
2000
|
480000
|
|
Unskilled
Labor
|
44
|
1000
|
528000
|
|
Guard/
Peon
|
6
|
1500
|
108000
|
|
Total
|
84
|
|
2016000
|
b) Administrative :
|
Category
|
No.
|
Monthly wages
|
Annual Cost
|
|
General Manager
|
1
|
30000
|
360000
|
|
Commercial Manager
|
1
|
25000
|
300000
|
|
Procurement Officer
|
1
|
12000
|
144000
|
|
Accountant
|
2
|
12000
|
288000
|
|
Store Keeper
|
4
|
5000
|
240000
|
|
Computer Operator
|
2
|
5000
|
120000
|
|
Peon
|
5
|
2000
|
120000
|
|
Total
|
16
|
|
1572000
|
|
Grand Total
|
100 Pers.
|
|
3588000/-
|
15. Estimated cost of the project:
Financial
Plan:
|
Sl
No
|
Items
|
Local
Currency
|
Foreign
currency
|
Total’
00000
|
|||
|
A
|
Fixed
Cost
|
Debt
|
Equity
|
Debt
|
Equity
|
Debt
|
Equity
|
|
|
Land
|
-
|
15
|
-
|
-
|
-
|
15
|
|
|
Building
|
20
|
10
|
-
|
-
|
20
|
10
|
|
|
Machinery
|
10
|
2
|
20
|
5
|
30
|
7
|
|
|
Other
Assets
|
2
|
1
|
-
|
-
|
2
|
1
|
|
|
Pre-
Prod Exp.
|
2
|
2
|
-
|
-
|
2
|
2
|
|
|
Contingency
|
10
|
-
|
-
|
-
|
10
|
-
|
|
|
Sub-Total
|
|
|
|
|
64
|
35
|
|
B
|
Working
Capital
|
Local
Currency
|
Local
Currency
|
Total’
00000
|
|||
|
|
|
Debt
|
Debt
|
Debt
|
Equity
|
Debt
|
Equity
|
|
1.
|
Raw
Materials
|
|
|
|
|
|
|
|
a.
|
Import
|
-
|
-
|
-
|
-
|
-
|
-
|
|
b.
|
Local
|
25
|
4.40
|
-
|
-
|
25
|
4.4
|
|
2.
|
Wages
|
30
|
5.88
|
-
|
-
|
30
|
5.88
|
|
3.
|
Other
Cash Exp.
|
-
|
.05
|
-
|
-
|
-
|
.5
|
|
|
Sub-Total
|
|
|
|
|
55
|
10.78
|
|
Total
|
A+B
|
|
|
|
|
119
|
45.78
|
17.
Utilities & Infrastructure:
a. Water: Available but
connection required.
b. Power: Available but
connection required.
c. Gas: Available but
connection required.
d. Road Way/ Rail Ways: It is
beside Dhaka Ctg High way.
18.
Manufacturing Process:
![]() |
|
![]() |
19.Estimated
Production / Sale
|
a. Items:
|
b. Quantity
|
c. Unit Rate
|
d. Total Cost
|
|
Holud
|
500000
|
20
|
10000000
|
|
Morich
|
500000
|
15
|
7500000
|
|
Dhonia
|
200000
|
15
|
3000000
|
20.
Schedule of Implementation (12 months);
1st month to 4th month:
Infra-structure Development & Import
Machineries.
5th month to 6th month:
Installation & Raw materials collection.
7th month to 8th month: Trial
operation & Agent/ Distributor
Selection.
9th month to 12th month:
Production & Marketing.
21.
Demand & Supply of the Product (Year):
1. Estimation Of Demand: 2000000 unit
2. Estimation Of Supply: 1500000 unit
22.
Marketing & Selling Arrangement: We have another enlisted distributed co.
as PR Co. which will
look after the distribution on commission basis.
23.Earning
Forecast:
i)
Sales: 25000000
ii)
Cost of Goods Sold: 15000000
iii)
Gross Profit: 10000000
iv)
General Admin & Selling Expences: 1500000
v)
Operating Profit: 8500000
vi)
Financial Expenses: 6000000
vii)
Net Profit before Tax: 2500000
viii)
Taxation: 50000
ix)
Net Profit After Tex:2450000
24.
Employment Generation: 100 No. of Persons
25.
Benefit of the project
a. Social Aspect: There is no negative
impact of the project on the society. The farmer can sell their cultivated
crops in rational aspect.
b. Marketing Aspect: The main products of the
project are Holud, Morich & Dhonia packet. Although there are three giant
companies in Bangladesh but the demand is still increasing. We hope to provide
lower price than the giant companies.Day by day bachelor and the job-holders
are increasing who wants ready spices.
c. Organizational Aspect: We will work together with
other organizations on the basis of win-win
situation.
d. From Commercial Point of
view:
|
Year
|
Fixed
Cost
|
Variable
Cost
|
Total
Cost
|
Total
Return
|
Net
Return
|
|
|
|
|
O
& M Cost
|
Production
Cost
|
|
|
|
|
01.
|
99
|
36.38
|
29.4
|
164.78
|
250.00
|
85.22
|
|
02.
|
90
|
30.00
|
70.0
|
190.00
|
290.00
|
100.00
|
|
03
|
85
|
30.00
|
105.0
|
220.00
|
330.00
|
110.00
|
e. Economic Point of View: The project after
implementation will create new job opportunity for 200 persons of different
categories and will contribute to Tk. 89.5 lac per year to GDP.
f. Environmental Aspect: No bad impacts will occur
on the environment and human safety by the project.
g. Legal Aspect: the company is enlisted
farm of the join stock company. The site of the project is in the industrial
area. The NOC obtained from Environment Department. BSTI certificate will
obtain while going to production.
h. Infrastructure Aspect: For super communication
BSCIC is ready to implement such project.